What Is The Minimum Cost Of Crashing The Following Project That Roger Solano Manages At Slippery Rock University

Monday July 11, 2022

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? PX ACTIVITY CRASH NORMAL TIME (DAYS) NORMAL COST CRASH COST IMMEDIATE PREDECESSOR(S) TIME (DAYS) A 6 5 $ 900 $1,000 B 8 6 300 400 C 4 3 500 600 – D 5 3 900 1,200 ? A E 00 5 1,000 1,600